In brief
The size comes from the loads that must stay on in a power cut, not the size of the building. An engineer lists those loads, adds them up in kW, allows for motors starting, and converts to kVA at the set's power factor. Then they add a margin and explain it.
On this page
Most people start with the building: how big it is, how many floors, how many staff. It feels like the obvious place to begin. But the size of a standby generator has very little to do with the size of the building, and a lot to do with what has to keep running when the mains goes.
This post walks through how a set is sized for a commercial, public or farm building, and what to ask the engineer who does it.
Start with what must stay on
The first question is a decision for you, not the engineer. If the power fails, what has to keep working? For a care home it might be lighting, nurse call, heating controls and the kitchen. For a data room, the IT load and its cooling. For a dairy farm, the milking parlour and cooling tanks.
Everything else can wait, and leaving it off the standby supply can make the set much smaller. In other words, the decision about what is essential is also a decision about cost.
How a load survey works
Once you know what is essential, an engineer measures or adds up what those circuits draw. A proper survey usually covers a few things.
- Running loads in kW for each essential circuit.
- Starting loads for motors, pumps, compressors and lifts, which can draw much more for a moment than when running.
- The order things start, because staggering them can reduce the peak the set has to meet.
- Future plans, such as more equipment or an extension.
The output is a figure in kW, and a note of the largest starting load the set has to cope with.
From kW to kVA
Generators are rated in kVA. Many are rated at a power factor of 0.8, so you divide the kW figure by 0.8 to get the minimum kVA. Our post on converting kVA to kW explains the sums in more detail.
| Essential load (kW) | Minimum at 0.8 power factor (kVA) |
|---|---|
| 16 | 20 |
| 40 | 50 |
| 80 | 100 |
| 200 | 250 |
| 400 | 500 |
Those are floors, not recommendations. The engineer then adds a margin for starting loads and growth, and should be able to tell you what margin they used and why.
Standby and prime ratings
You may notice that the same set can be quoted with two different figures. BS ISO 8528-1 defines different ratings for generating sets, including standby, for sets that only run when the mains fails, and prime, for sets that run as the main supply for long periods.
Check which rating a quote refers to. A set bought on its standby rating may not suit a farm or remote site that runs it for long hours as its main supply.
A worked example
Here is a simple illustration, with figures made up for the example. An office wants its server room, emergency lighting, one lift and its security systems on standby.
- Server room and its cooling: 24 kW
- Lighting on the essential circuits: 6 kW
- Security and access control: 2 kW
- One lift, running: 8 kW
That adds up to 40 kW running, or 50 kVA at 0.8. But the lift motor and the cooling compressors draw more as they start. So the engineer would size above 50 kVA, perhaps staggering starts to keep the peak down, and explain the figure they chose.
The rest of the design
Picking a size is only the first part of the job. Our page on generator installation covers the rest, but these are the points that most often come up.
- The changeover. A switch or automatic transfer switch must keep the set and the mains apart. BS 7671 Section 551 covers low voltage generating sets.
- Running in parallel. If the set will ever run alongside the mains, the network operator’s rules (Engineering Recommendation G99) apply.
- Fuel. In England, a business tank over 200 litres above ground usually needs secondary containment such as a 110% bund, with some exemptions.
Too big is a problem too
It’s tempting to buy a bigger set “to be safe”. But a diesel set that spends its life running far below its rating can suffer from light-load running, with unburnt fuel building up in the exhaust. That is one reason sizing is worth getting right, and why a yearly load bank test is useful on sets that rarely see real load.
Getting a set sized properly is the kind of job a generator servicing company engineer does every week. If you’d like someone to carry out a load survey for your building, send the details through the form below.