How do you convert kVA to kW for a generator?

Ratings4 min readRevised Written by Generator Servicing Company

A site generator on a construction site

In brief

Multiply kVA by the power factor to get kW. Many generators are rated at a power factor of 0.8, so 100 kVA gives about 80 kW. To go the other way, divide kW by 0.8. Check the rating plate, because the power factor of your set may differ.

On this page
  1. kVA and kW are not the same thing
  2. The formula
  3. Quick conversion table at 0.8 power factor
  4. Why it matters when you buy or test a set
  5. A worked example
  6. Where people go wrong

Generators are sold and rated in kVA, but most of the equipment in your building is described in kW. If you are trying to work out whether a set is big enough, or what a quote is really offering, you need to move between the two.

This post explains the difference, gives the formula, and works through a building example.

kVA and kW are not the same thing

kW (kilowatts) is real power: the part that does useful work, running motors, lights and servers.

kVA (kilovolt-amperes) is apparent power: the total the generator has to supply, including a part that flows back and forth without doing useful work. That second part is called reactive power and is measured in kVAr.

The link between them is the power factor, a number between 0 and 1. The closer it is to 1, the more of the generator’s output is doing useful work.

The formula

The sums are simple once you know the power factor.

  • kW = kVA × power factor
  • kVA = kW ÷ power factor

Many three-phase generators are rated at a power factor of 0.8. So at that rating, kW is 80% of kVA. BS ISO 8528-1, the standard on generating set ratings and performance, is where ratings such as standby and prime power are defined, and your set’s rating plate gives the figures that apply to it.

80 kW (real power) 60 kVAr reactive 100 kVA (apparent)
At a 0.8 power factor, 100 kVA splits into 80 kW of real power and 60 kVAr of reactive power, because 80² + 60² = 100².

Quick conversion table at 0.8 power factor

This table uses a 0.8 power factor throughout. If your rating plate shows a different figure, use that instead.

Set rating (kVA) Real power (kW)
20 16
30 24
60 48
100 80
250 200
500 400
1,000 800

Going the other way, a building load of 40 kW needs at least 50 kVA at 0.8, and 200 kW needs at least 250 kVA. Those are the bare minimums before any allowance for starting motors or future growth.

Why it matters when you buy or test a set

You may find two quotes that seem to offer the same size of set but describe it differently, one in kVA and one in kW. Putting both into the same unit is the first step to comparing them fairly.

It matters for testing too. A load bank test is planned against the set’s rating, and one public tender asked for a yearly four-hour test on each standby set up to 110% of full load. Knowing what “full load” means in kW for your set helps you read the test report. Our load bank testing page has more.

A worked example

Say a small data room and its cooling must stay on in a power cut. The engineer adds up the essential loads and gets 64 kW.

At a 0.8 power factor, 64 ÷ 0.8 = 80 kVA. So an 80 kVA set would only just cover the running load, with nothing to spare for the moment the cooling compressors start, or for the next rack of equipment. In practice the engineer would size above that figure and explain the margin they have allowed and why.

That is the general method; our post on what size standby generator a building needs goes through it step by step.

Where people go wrong

These are the slips we see most often in requests.

  • Treating kVA as kW. A 100 kVA set will not run 100 kW of load at 0.8.
  • Forgetting starting loads. Motors can draw much more for a moment as they start than when running.
  • Ignoring the rating type. A standby rating and a prime rating are not the same, so check which one the figure on the quote refers to.

Those are exactly the questions a good generator servicing company engineer will raise before recommending a size.

Have a rating plate you can’t make sense of? Send the details through the form and an engineer can read it for you.

Sources for this post

Ask for a quote for your generator

We look for one service engineer who works in your area and tell you who they are before any of your details go to them. You pay nothing for this.

  1. You tell us where the set is and what it needs.
  2. We name an engineer who covers your site.
  3. You say yes or no before your details are passed on.
  4. They quote in writing, directly to you.

Step 1 of 3

Where is the generator?
Get a quote